Inland large-scale project transportation work

 

Inland large-scale project transportation work - from wharf warehouse to ship side

 

Entrusted by CHRobinson Canada, our company uses ten axis SPMT to assist customers in delivering their two 350 ton separators and their accessories to the ship's side from the customer's warehouse at No. 75 Wharf in Kaohsiung.

The dimensions of the separator are as follows: 17,360 mm(L) x 10,710 mm(W) x 9,420 mm(H),350 tons x two sets.

 

The ocean vessel berthed to the wharf at about 4:30 on Dec / 29. Our company transported the first separator to the wharf at 17:30 according to the instructions of the captain of Paula for ready loading. The next day, we started at 08:30 and continued to complete the remaining separator and its accessories (including two wooden boxes and mold frames). The vessel left the port at 21:13 on Dec / 30 on that day.

 

   
 
 

 

 

   
   
   

 